The Victor by Windsor

Aaon RTU Replacement

110 Beverly Street
Boston, Massachusetts 02114

https://www.thevictorbywindsor.com

Property Details

286 Units

Opportunity Details

Secure power  Reclaim R410A and dispose of off-site per EPA standards Furnish and install a direct replacement Aaon RN-025 rooftop unit A crane service will file for engineered drawings permits and a police detail to set up and lift new RTU and remove old and dispose of off-site Condenser Evaporator and reheat coils will have a polymer protective coating for protection from the elements Once installed the unit will be started by a Factory representative operation checked and left online to serve space belowNote Crane Lifting Plan Engineering survey cost included cannot guaranty time line Unit has a 20- 25-week lead time once ordered The MCA and MOP are higher on the new unit than on the existing breaker and power wire size  will need to be increased By others